Standard Transmission Charges

The CER has today (15th January 2013) published an information note which outlines the Standard Transmission Charges for 2013 that EirGrid will use when issuing offers for connection to the Irish distribution (where shallow transmission assets are built) and transmission networks.

Queries on this paper should be submitted to Lisa Fahy (lfahy@cer.ie ) in the CER.

To view this document, please click on the below:

The intent of standard transmission connection charges (and timelines) is to provide a reasonable degree of certainty for parties seeking to connect to the distribution and transmission systems in Ireland.  In particular, they provide the basis for connection charges for Gate 3 distribution (where shallow transmission assets are built) and transmission related renewable Generator connection offers.

Previous charges can be viewed below:

The charges contained in CER/09/077 were indicative 2009 prices.  These have now been updated to reflect indicative yearly prices.

See also...